In order to ensure the realization of the project schedule, a resource demand plan corresponding to the schedule plan should be prepared. If the resource conditions are not met, ( ) should be adjusted.


A、Thescheduleplan;
B、Theschedulegoal;
C、Thecostplan;
D、Theresourceplan

发布时间:2025-07-06 23:39:15
推荐参考答案 ( 由 题搜搜 官方老师解答 )
答案:The schedule plan